By LE Construction · Published October 6, 2026
“Can it be done by the holidays?” is one of the most common questions we hear in late summer and fall. Sometimes the answer is yes. Often, for bigger projects, the honest answer is “only if we started planning months ago.” Here is how to think about it.
Work backward from the date
Every remodel has steps before construction:
- Estimate and decisions.
- Design and selections.
- Ordering materials, some with long lead times.
- Permits, for most kitchens and many bathrooms.
- Construction and inspections.
Add those up from your target date and you have your real start date.
What is realistic on a short timeline
- Paint and drywall repair.
- New lighting fixtures.
- A powder room refresh with in-stock fixtures.
- Some flooring, if the material is available.
What needs months of lead time
- Full kitchen remodels, especially with layout changes or custom cabinets.
- Primary bathroom remodels with custom tile and glass.
- Anything structural, like removing a wall.
- Additions.
How to protect the deadline
- Decide early. Changing selections mid-project is the most common cause of delay.
- Order before demolition. We order cabinets, counters and fixtures before the room is torn apart.
- Choose in-stock where it matters.
- Plan for the unexpected. Older homes can hide conditions that add time.
A good alternative
If the timeline is tight, consider using the holidays to plan and making selections in December, then starting construction in January. You get a calmer holiday and a better-planned remodel.
See how long a kitchen remodel takes and how long a bathroom remodel takes.
Frequently asked questions
Can I get a full kitchen remodel done before Thanksgiving if I start in October?
Usually not, once you account for design, ordering, permits and construction. A cabinet and counter swap might fit if everything is decided and in stock. A full remodel should be planned months earlier.
What projects can realistically be finished in a few weeks?
Drywall repairs, paint, a powder room refresh, new lighting and some flooring jobs. Projects without permits or long-lead materials are the most predictable.
What usually delays holiday remodels?
Late material selections, back-ordered items, permit timing and hidden conditions found during demolition. Deciding early and ordering before demolition removes most of the risk.
Is it better to finish before the holidays or start after?
If the deadline is tight, starting in January after the holidays can be less stressful and leave time for proper planning. Many owners use the holiday season to make selections.